The Project Statistics page provides statistical data
for the current project.
The Project Statistics page includes 3 elements:
The title bar shows the page title. The following link is available at the end of the title bar:
- The (
Help ) link lets you reach the contextual help.
The Project group provides the number and the name of the current project.
|
Project Number
|
Soft-001
|
|
Project Name
|
Software development
|
The Statistics tables provide statistical data for the current project.
- The "General Statistics" table provides the overall project statistics while the other tables
provide project statistics broken down by "Project Users", "Task Groups", "Task Types", "Task Statuses"
and "Task Priorities".
The "General Statistics" table
The "General Statistics" table provides the overall project statistics.
- The "Total Tasks" field shows the total number of existing tasks within the current project (both "incomplete"
and "completed").
- The "Total Incomplete Tasks" field shows the total number of existing tasks within the
current project that bear either a "Waiting" or an "In Progress" status.
|
Total Incomplete Tasks
|
10
|
- The "Total Completed Tasks" field shows
the total number of existing tasks within the current project
that bear a "Completed" status (in other words, closed tasks).
- The "Total Documents" field shows the number of "Task Documents" and "Project Documents"
within the current project, as well as the total storage space these documents are using.
|
Total Documents
|
4 document(s), 0.22MB
|
- The "Estimated Total Hours" field shows the sum of all task "Estimated Hours"
within
the current project.
|
Estimated Total Hours
|
104.00
|
- The "Actual Total Hours" field shows the sum of all work hours entered by users in
time sheets, for all tasks within the current project.
- Only work items that bear the "In progress", "Submitted or "Approved status are included
in the computation. Rejected time is not included in the computation.
- The "Estimated Average % Done" field shows the average "% Done"
of all tasks within
the current project.
|
Estimated Average % Done
|
63.37%
|
- The computation is made as follows: S (estimated hours X %done) / total hours
- The "Actual Average % Done" shows the average "Actual % Done" for all tasks within the
current project.
|
Actual Average % Done
|
22.16%
|
- The computation is made as follows: S (actual hours / estimated hours) / total tasks
The "Project Users Statistics" table
The "Project Users Statistics" table provides project statistics, broken down by
assigned user. By default, only active users are displayed. Inactive users'
statistics may be displayed by clicking on the "Show Inactive Users" link
located below the table.
|
Username
|
Project Manager
|
Created Tasks
|
Assigned Tasks
|
Tasks to Review
|
Actual Hours
|
Assigned Hours
|
|
Jane
|
No
|
3
|
4
|
2
|
10.32
|
13.00
|
|
Jeff
|
Yes
|
0
|
2
|
1
|
0.00
|
52.00
|
- The "Project Manager" column mentions whether the user is assigned as a "Project Manager" on the actual
project or not.
- The "Created Tasks" column shows the total number of tasks each user created within
the current project.
- The "Assigned Tasks" column shows the total number of tasks assigned to each
user, within the current project.
- The "Tasks to Review" column shows the total number of tasks each user
has to review,
within the current project.
- The "Actual Hours" column shows the total number of work hours each user entered
in their time sheets, for all tasks within the current project.
- Only work items that bear the "In progress", "Submitted or "Approved status are included
in the computation. Rejected time is not included in the computation.
- The "Assigned Hours" column shows the total number of hours
assigned to each user,
for all tasks within the current project.
The "Task Groups Statistics" table
The "Task Groups Statistics" table provides project statistics, broken down by "Task Group".
|
Name
|
Total Tasks
|
Estimated Total Hours
|
Actual Total Hours
|
Estimated Average % Done
|
Actual Average % Done
|
|
Design
|
1
|
3.00
|
0.00
|
0.00%
|
0.00%
|
|
Architecture
|
5
|
69.00
|
8.53
|
85.51%
|
12.36%
|
- The "Total Tasks" column shows the total number of tasks associated with each "Task Group",
within the current project.
- The "Estimated Total Hours" column shows the total number of "Estimated Hours" for all
tasks that belong to each "Task Group", within the current project.
- The "Actual Total Hours" column shows the total number of work hours entered
by assigned users in their time sheets, for all tasks
associated with each "Task Group", within the actual
project.
- Only work items that bear the "In progress", "Submitted or "Approved status are included
in the computation. Rejected time is not included in the computation.
- The "Estimated Average % Done" column shows the average "% Done" for all tasks
associated with each "Task Group", within the current project.
- The computation is made as follows: S (estimated hours X %done) / total hours
- The "Actual Average % Done" column shows the average "Actual % Done" for all tasks
associated with each "Task Group", within the current project.
- The computation is made as follows: S (actual hours / estimated hours) / total tasks
The "Task Types Statistics" table
The "Task Types Statistics" table provides project statistics, broken down by "Task Type".
|
Name
|
Total Tasks
|
Estimated Total Hours
|
Actual Total Hours
|
Estimated Average % Done
|
Actual Average % Done
|
|
Modification
|
3
|
16.00
|
0.00
|
0.00%
|
0.00%
|
|
Improvement
|
3
|
69.00
|
8.53
|
85.51%
|
12.36%
|
- The "Total Tasks" column shows the total number of tasks associated with each "Task
Type",
within the current project.
- The "Estimated Total Hours" column shows the total number of "Estimated Hours" for all
tasks that belong to each "Task Type", within the current project.
- The "Actual Total Hours" column shows the total number of work hours entered
by assigned users in their time sheets, for all tasks
associated with each "Task Type", within the actual
project.
- Only work items that bear the "In progress", "Submitted or "Approved status are included
in the computation. Rejected time is not included in the computation.
- The "Estimated Average % Done" column shows the average "% Done" for all tasks
associated with each "Task Type", within the current project.
- The computation is made as follows: S (estimated hours X %done) / total hours
- The "Actual Average % Done" column shows the average "Actual % Done" for all tasks
associated with each "Task Type", within the current project.
- The computation is made as follows: S (actual hours / estimated hours) / total tasks
The "Task Statuses Statistics" table
The "Task Statuses Statistics" table provides project statistics, broken down by "Task Status".
|
Name
|
Type
|
Total Tasks
|
Estimated Total Hours
|
Actual Total Hours
|
Estimated Average % Done
|
Actual Average % Done
|
|
To Do
|
Waiting
|
5
|
27.00
|
3.00
|
0.00%
|
11.11%
|
|
In progress
|
In Progress
|
3
|
57.00
|
8.78
|
83.86%
|
15.40%
|
|
Finished
|
Completed
|
3
|
15.00
|
1.70
|
100.00%
|
11.33%
|
- The "Total Tasks" column shows the total number of tasks associated with each "Task
Status",
within the current project.
- The "Estimated Total Hours" column shows the total number of "Estimated Hours" for all
tasks that belong to each "Task Status", within the current project.
- The "Actual Total Hours" column shows the total number of work hours entered
by assigned users in their time sheets, for all tasks
associated with each "Task Status", within the actual
project.
- Only work items that bear the "In progress", "Submitted or "Approved status are included
in the computation. Rejected time is not included in the computation.
- The "Estimated Average % Done" column shows the average "% Done" for all tasks
associated with each "Task Status", within the current project.
- The computation is made as follows: S (estimated hours X %done) / total hours
- The "Actual Average % Done" column shows the average "Actual % Done" for all tasks
associated with each "Task Status", within the current project.
- The computation is made as follows: S (actual hours / estimated hours) / total tasks
The "Task Priorities Statistics" table
The "Task Priorities Statistics" table provides project statistics, broken down by "Task Priority".
|
Name
|
Total Tasks
|
Estimated Total Hours
|
Actual Total Hours
|
Estimated Average % Done
|
Actual Average % Done
|
|
Critical
|
4
|
11.00
|
4.32
|
12.73%
|
39.27%
|
|
Urgent
|
1
|
4.00
|
2.00
|
0.00%
|
50.00%
|
|
High
|
1
|
4.00
|
0.00
|
100.00%
|
0.00%
|
|
Normal
|
4
|
71.00
|
12.53
|
69.72%
|
17.65%
|
|
Low
|
3
|
14.00
|
1.70
|
78.57%
|
12.14%
|
- The "Total Tasks" column shows the total number of tasks associated with each "Task
Priority",
within the current project.
- The "Estimated Total Hours" column shows the total number of "Estimated Hours" for all
tasks that belong to each "Task Priority", within the current project.
- The "Actual Total Hours" column shows the total number of work hours entered
by assigned users in their time sheets, for all tasks
associated with each "Task Priority", within the actual
project.
- Only work items that bear the "In progress", "Submitted or "Approved status are included
in the computation. Rejected time is not included in the computation.
- The "Average Estimated % Done" column shows the average "% Done" for all tasks
associated with each "Task Priority", within the current project.
- The computation is made as follows: S (estimated hours X %done) / total hours
- The "Actual Average % Done" column shows the average "Actual % Done" for all tasks
associated with each "Task Priority", within the current project.
- The computation is made as follows: S (actual hours / estimated hours) / total tasks
|